North Regional Lift Station and Force Main Replacement – Mebane

AWCK provided construction drawings, specifications and bid documents, and construction related services for the City of Mebane’s North Regional Lift Station and Force Main Replacement project. The project consists of relocating, replacing, and upgrading the previous lift station to a 1730 GPM capacity lift station and installation of approximately 14,000 lf of force main from station to the wastewater treatment plant. The project was completed in 2013 and included paralleling an existing 16” sanitary sewer line, vast amounts of rock for both the lift station and force main installation, coordination with the contractor for constraints related to school traffic, residential neighborhoods, and boring under the NC Rail Road.


Project Contact: David Cheek, City Manager
Phone Number: (919) 563-5901

Project Manager: Darrell Russell, PE
Project Engineer: Mark Averette, PE
Completion: 2008
Construction Cost: $2.8 Million
NE Pump and Lift Mebane