Town of Gibsonville—Water System Enhancement Projects

AWCK has assisted the Town of Gibsonville with the design, construction drawings, specifications and bid documents for approximately 3,200 LF of water line replacement. In addition to the new water lines, AWCK produced documents for the installation of a new master meter connection to the City of Burlington’s domestic water system. The water lines removed old galvanized lines from the system and the new meter improved pressure and fire flows within the system.

Projects:
Bethel Church Road Replacement (2009): 1,200 LF of 2” to 6” water line replacement.
Multiple Water Improvement (2007): 2,000 LF of 6” and 8” water line replacement.
Meter Project (2009): Installation of new 12″ master meter for Gibsonville.

Project Contact: Mr. Benjamin Baxley. Town Manager
Phone Number: (336)449-4144

AWCK Contact: Mark Averette, P.E.

Gibsonville Water Enhancements